Step 2 Drill holes in the mounting hole marks by using a hammer drill.
This installation scenario uses common bolts rather than expansion bolts.
Step 3 Use a pallet truck to move the cabinet to the installation position.
Step 4 Use eight M12x45 bolts to secure the cabinet to the mounting holes in the channel steel and
tighten the bolts.
Step 5 Install the front and rear anchor baffle plates and left and right anchor baffle plates, as shown
in
Step 6 (Recommended) Install a lock for the maintenance bypass switch to prevent misoperations, as
shown in
----End

3.2.2 Installing Batteries

Context
Procedure
Step 1 Install a battery rack and batteries.
For details, see the battery installation guide delivered along with batteries.
----End
Issue 06 (2020-01-10)
The external sides of front and rear channel steels must be aligned with the column. The
channel steel spacing is 800 mm. The recommeneded channel steel width is 50 mm or
more.
Cabinet mounting holes must align channel steels. Tighten screws to secure the base to
channel steels.
Figure
3-22.
Figure
3-23. The required lock core diameter is 5–10 mm.
Before installing batteries, read through the battery safety precautions, obtain the delivered
battery installation guide, and install batteries as instructed.
Place the batteries in a correct way to prevent vibrations and shocks.
Install the batteries from the lower layer to the upper layer to prevent falling over due to
imbalance.
Copyright © Huawei Technologies Co., Ltd.
3 Installation
61

Advertisement

Table of Contents
loading

Table of Contents