8 Commissioning

Prerequisites for commissioning

8.
Commissioning
8.1
Prerequisites for commissioning
All inverters in the system are connected with one another
via RS485.
All inverters are supplied with AC or DC voltage.
The PC is connected to the RS485 network of the inverters
via a USB/RS485 adapter.
Commissioning the inverter requires a PC with the com-
missioning software and Delta Service Software (DSS) in-
stalled. Both can be downloaded from
delta-emea.com/en/Solar-Inverter-Support-171.htm.
8.2
Commissioning with the Delta Service
Software (DSS)
Prerequisites
During installation, a Windows PC on which the Delta Service
Software is installed was connected to the inverter (see "7.7.7
Connecting a PC via RS485 (optional)", page 75).
Download link
https://solarsolutions.delta-emea.com/en/Solar-
Inverter-Support-171.htm
Procedure
► Launch the Delta Service Software and follow the instruc-
tions.
84
https://solarsolutions.
► Turn both DC disconnectores to the ON position.
Installation and Operation Manual M50A_260 RPI503M260000 Product version L and M EU V1.3 EN 2023-08-14