Commissioning
4 Commissioning
- Double confirm the all connections are correct before the commissioning. If there
is any abnormal during the commissioning, Safely power OFF AC and DC energy
is always the first priority. Please switch off AC breaker and Two DC switches,
then check the installation and find out the cause.
While the installation is done, please follow sequence to execute the commissioning.
1. Ensure the front door is close well, Section 5.1.3 has further description to guide
2. Turn on the AC breaker to supply AC voltage.
3. Switch On two DC switches on the right hand side.
CAUTION !
Figure 4-1:DC Switches
48
ON
OFF