Chapter Three Operation & Use Method of Power tiller
Ⅰ. Assembly After Unpacking (see Figure 4)
Figure
4
1. Fix the main machine, insert the hexagonal output shaft into stepped box's output casing's
hexagonal hole.
2.Fix the hexagonal stop casing onto the hexagonal output shaft with M6×6 socket head
screws, and make the hexagonal shaft not move axially.
3 .Wheel fixing: fix the wheels at the two sides of the Hexagonal output shaft, and fix them with two M8×55
bolts and M8 nuts.
4. Trailer fixing: Fix the link group onto the trailer, use the link shaft assembly for connection, insert the
split pin
3×26 and insert the velocity adjustment screw into square groove of the link group, and fix it
with M8×55 bolts and nuts.
5. Handle bar fixing: Two gear discs of the handle bar support aim at the discs of the
handle bar support base, and adjust the positions. Fix them with M16×140 bolts, flat gasket 16 and spring
gasket16.
6. Shifting bar assembly: Get the shifting bar through the groove of shift support in the

Advertisement