Step 9. Ground the AC Modules
Ground the AC Modules per the module manufacturer's instruction.
Step 10: Energize the system
A. Turn ON the AC disconnect or circuit breaker for the branch circuit.
B. Turn ON the main utility-grid AC circuit breaker. Your system starts producing power after a five-
minute wait time.
C. Check the LED on the connector side of the microinverter.
LED color
Flashing green
Flashing orange
Flashing red
Solid red
Step 11: Set up and activate monitoring
Refer to the Enphase IQ
and grid management functions. This guide leads you through the following:
•
Connecting the IQ
•
Detecting devices and scanning the installation map
•
Connecting to Enphase Installer Portal
•
Registering the system
•
Building the virtual array
20
Indicates
Normal operation. AC grid function is normal there is communication with the IQ
Gateway.
The AC grid is normal but there is no communication with the IQ Gateway.
The AC grid is either not present or not within specification.
There is an active "DC Resistance Low - Power Off" condition. To reset, see
Resistance Low – Power Off condition.
Quick Install Guide to install the IQ
Gateway
Gateway
© 2023 Enphase Energy Inc. All rights reserved.
IQ Microinverters for AC Module applications
and set up system monitoring
Gateway
DC
June 2023
USM-00001-1.0