6-7. TEMPERATURE PROBE
REPLACEMENT
(Continued)
6-8. SOLENOID VALVES
Nov. 2009
9. Connect new temperature probe to the connector and fasten
connector onto control panel.
10. Replace control panel and reconnect power to vat.
11. Fill vat by pressing and holding
TER* *MENU* shows in the display. Then once "1.EX-
PRESS FILTER" shows in the display, press ►4 times until
"5.FILL FROM PAN" shows in the display. Press √ button
and "PUMP" "EXIT" shows in the display. Press √ button
again, and oil fills vat. Once vat is full,
return to normal operation.
Each vat has a solenoid plumbed-into the oil return lines. They
are normally closed, but open when power is supplied, such as,
the controls are filling the vats.
To avoid electrical shock or property damage, move the
power switch to OFF and disconnect main circuit
breaker, or unplug cord at wall receptacle.
1. Remove both top and bottom rear panels, or a side panel,
depending upon the location of the solenoid.
Checkout
2. Follow the wires from the solenoid and through the conduit
and then cut the wires. Strip the wires back and take an
ohm reading:
120 Volts - 60Hertz
220-240 Volts -50/60 Hertz
6-9
Model EEG-142, 143, 144
button until *FIL-
press X twice to
50 Ohms
230 Ohms