Acceptance Test - Completion Of Commissioning; Prerequisites And Authorized Persons - Siemens SINAMICS G120 Function Manual

Hide thumbs Also See for SINAMICS G120:
Table of Contents

Advertisement

Commissioning

4.9 Acceptance test - Completion of commissioning

4.9
Acceptance test - Completion of commissioning
4.9.1

Prerequisites and authorized persons

Requirements for acceptance tests are derived from the EC Machinery Directive and
ISO 13849-1.
● Check the safety-related functions and machine parts following commissioning.
● Issue an "Acceptance certificate" which describes the test results.
Prerequisites for the acceptance test
● The machine is properly wired.
● All safety equipment such as protective door monitoring devices, light barriers or
● Commissioning of the open-loop and closed-loop control must be complete. These
Authorized persons
Authorization within the scope of the acceptance test is a person authorized by the machine
manufacturer who, on account of his or her technical qualifications and knowledge of the
safety functions, is in a position to perform the acceptance test in the correct manner.
164
emergency-off switches are connected and ready for operation.
include, for example:
– Configuration of the setpoint channel.
– Position control in the higher-level controller.
– Drive control.
Safety Integrated Function Manual, SINAMICS G120 and G120C
Function Manual, 01/2011, FW 4.4, A5E03052391B AB