Elastomeric Isolator Installation; Figure 38 - Elastomeric Isolator - York YVAA Installation Operation & Maintenance

Air-cooled screw liquid chillers, air-cooled screw liquid chillers with variable speed drive
Table of Contents

Advertisement

SECTION 5 - TECHNICAL DATA
D

Figure 38 - Elastomeric isolator

Read the following instructions before beginning
installation.
1. Isolators are shipped fully assembled and are to be
positioned in accordance with the submittal draw-
ings or as otherwise recommended.
2. Set isolators on floor, housekeeping pad or sub-
base, ensuring that all isolators lines match the
equipment mounting holes. Johnson Controls
recommends that the isolator base (A) is installed
on a level surface. Shim or grout as required,
leveling all isolator bases to the same elevation.
0.03125 of an inch maximum difference can be
tolerated.
88

Elastomeric isolator installation

(B)
D
C L
(C)
C L
SECTION D-D
Section D-D
3. Bolt or anchor all isolators to supporting structure
utilizing base through holes (B).
4. Remove top bolt and top washer. Place equip-
ment on top of isolators so that mounting holes in
equipment or base line up with threaded hole (C).
5. Reinstall top bolt and washer and tighten down.
Form 201.47-ICOM1
Issue date: 17/11/2022
Top bolt
Top washer
(B)
(A)
LD13762C