Observe ambient temperature. Ensure adequate cooling.
Connect bus line, observing the correct polarity.
Connect load as shown in the connection example (see figure 5).
If required, connect potential-free contacts or condensation/leakage sensors to
inputs 1...3, or NTC temperature sensors to input 3 (see figure 2).
Install the device in the appliance box.
In secure operation: The device certificate must be removed from the device
and stored securely.
The COM reference potential must not be connected together with COM con-
nections of other devices!
4.2

Commissioning

Commissioning the device
NOTICE!
Incorrect load control due to undefined relay state at delivery.
Risk of destruction of connected drive motors.
During commissioning, before switching on the load, ensure that all relay contacts
are open by applying the KNX bus voltage. Observe commissioning sequence!
82404232
Image 5: Connection of load
29.11.2022
9 / 13