Continuous regulator
Optional: Route an external temperature sensor in an empty pipe and guide the
sensor head out at the measurement location.
Select the installation location for the temperature sensor so that it can measure the
temperature without any influence from sources of interference.
Connect the external temperature sensor to the connection terminals 5 and 6
(see figure 5) of the terminal strip (10) (see figure 3).
The sensor cable can be extended up to a maximum of 50 m with a twisted
pair cable, e.g. J-Y(St)Y-2x2x0.8. When using the KNX bus line: use a second
pair of yellow/white cores.
Insert the connection terminal insert (4) (see figure 2) in the flush-mounted ap-
pliance box. Observe the labelling OBEN / TOP. The bus connection (11) must
be at the bottom, right (see figure 3).
Fit the cover frame (5) on the connection terminal insert (4).
Insert the electronics cover (6) in the correct position into the connection ter-
minal insert (4).
Remove the adjustment dial (2).
Fasten the electronics cover with the retaining screw (7).
Reattach the adjustment dial (2).
5.2

Commissioning

Loading the address and the application software
Pull off the adjustment dial (2) (see figure 2).
Press the programming button (9).
The programming LED (8) is illuminated.
Assign a physical address.
The programming LED (8) goes out.
Note down the physical address on the connection terminal insert and on the
back of the electronics cover.
Observe the correct assignment of inserts and covers when assembling after
painting or wallpapering.