Installation Suction Line (General Instructions) - ProMinent gamma G/4b Operating Instructions Manual

Metering pump
Table of Contents

Advertisement

S
S
T A I N L E S S
T A I N L E S S
S T E E L
S T E E L
P I P E
P I P E
PE/PTFE lines
Order no. 35.93.65.4
Order no. 35.93.66.2
Order no. 35.93.68.8
Page 26 of 88 pages
Installation
Please note:
You obtain a fixed hose connection if you pull shortly on the line
connected to the liquid end and subsequently retighten the union
nut "hand-tight"!
Stainless steel pipe connections:
C O N N E C T I O N S
C O N N E C T I O N S
• Push up the union nut and the gripper ring on to the pipe so that they
project approx. 10 mm.
• Insert the pipe into the valve until the stop and initially tighten the union
nut with your fingers.
For initial assembly continue to tighten the union nut another 1 1/
4 turns.
When remounting tighten 1/4 turn further.
PE/PTFE lines:
• When connecting to stainless steel valves additionally insert a stainless
steel ferrule into the plastic hose.
Ferrule for hose 6x4 mm
Ferrule for hose 8x5 mm
Ferrule for hose 12x9 mm

10.1.3 Installation suction line (general instructions)

Please note:
Keep the suction line as short as possible!
Size the diameter and length so that the underpressure arising
when sucking does not reach the steam pressure of the media to
be fed!
The suction line must be laid ascending in order to prevent air
bubbles from forming!
For bends use arcs and not angles if possible!
Please note:
Too high underpressure on the suction side in extreme cases
leads to the fluid column tearing or an incomplete return stroke!
NB:
Height (h) x density (d) ≤ max. suction lift in mWC!