Installation
Connector
set
• Lay lines in such a way so that if necessary the pump and lines can be
removed to the side.
• If the suction/discharge connection is closed with a plug please
remove this.
• Attach the suction line to the suction connection.
• Attach the discharge line to the discharge connection.
Hose lines
Hose lines:
• Pull the union nut and gripper ring over the hose line.
• Push the hose end cut straight onto the nozzle up to the stop.
• If necessary widen the hose end a little.
If used for several connections shorten the hose end approx. 10 mm
by cutting it straight.
• Push on the hose and simultaneously tighten the union nut.
Union nut >
Hose line >
Nozzle >
O-ring >
PLEASE NOTE:
Only use the gripper rings and hose nozzles for the respective
hose diameter as well as original hoses with specified hose
dimensions and wall thickness. If this is not observed the stability
of the connection is not guaranteed!
Avoid reducing the hose sizes!
For long lines and viscous media the next highest line diameter
should be used!