1.
Station number setting
Set the station numbers of the bridge module. ( Page 37, Section 6.1)
Set the station numbers of the CC-Link remote station. ( Manual for the CC-Link remote station)
2.
Installation
Install the bridge module on a DIN rail. ( Page 41, Section 6.3)
3.
Wiring
Connect a power supply, Ethernet cable, and CC-Link dedicated cable to the bridge module. ( Page
44, Section 6.4)
Connect a power supply, CC-Link dedicated cable, and external device to the CC-Link remote station.
( Manual for the CC-Link remote station)
4.
Parameter setting for CC-Link IE Field Network
Connect the master station to the engineering tool to set the parameters of CC-Link IE Field Network.
( Page 53, Section 7.1)
5.
Parameter setting for CC-Link
Set the parameters of CC-Link with the switch of the bridge module or using the engineering tool. (
Page 55, Section 7.2)
6.
Programming
Create a program. ( Page 65, CHAPTER 8)
To change the system, follow the procedure described below.
• Power off the system.
• Delete or add the CC-Link remote station and perform the procedure above from "Station number setting" to
"Programming".