Adjusting The Developer And Fixer Replenishment Rates - Kodak X-Omat 1000 Service Manual

Table of Contents

Advertisement

SERVICE MANUAL
Adding to Developer Temperature
SW04:
Set point Add/Subtract
Temperature
0
0.0°C (0.0°F)
1
0.1°C (0.18°F)
2
0.2°C (0.36°F)
3
0.3°C (0.54°F)
4
0.4°C (0.72°F)
5
0.5°C (0.90°F)
6
0.6°C (1.08°F)
7
0.7°C (1.26°F)

Adjusting the Developer and Fixer Replenishment Rates

1
2
3
4
SW05
H164_0039AC
Replenishment Rate
Set point of SW06
or SW07
0
1
2
3
4
5
6
7
8
9
* Volume for film size 35 x 43 cm (11 x 14 in.)
50
Set point Add/Subtract
Temperature
8
0.8°C (1.44°F)
9
0.9°C (1.62°F)
A
1.0°C (1.8°F)
B
1.1°C (1.98°F)
C
1.2°C (1.32°F)
D
1.3°C (2.34°F)
E
1.4°C (2.52°F)
F
1.5°C (2.70°F)
0
0
DEV
FIX
RPL
SW07
SW06
Volume in
60 Hz, SW02-1 OFF. Time for PUMP
3
cm
*
50
60
70
80
90
100
110
120
130
140
Important
The temperature is added or subtracted in 0.1°C
(0.18°F) increments.
[6] Use SW04 to add to or subtract from the
developer temperature.
(a) Move SW05-2 to the "OFF" position to
subtract from the developer temperature.
(b) Move SW05-2 to the "ON" position to add to
the developer temperature.
(c) Use the table at the left to set SWITCH
SW04.
[7] Install the CONTROL BOX COVER. See
Removing the CONTROL BOX
ESD
Possible damage from electrostatic discharge.
[1] Do
Removing the CONTROL BOX
[2] Use the Replenishment Rate table to set the
correct replenishment rate.
(a) Adjust SW06 to set the developer
replenishment rate.
(b) Adjust SW07 to set the fixer replenishment
rate.
[3] Install the CONTROL BOX COVER. See
Removing the CONTROL BOX
ON in seconds
7.0
8.4
9.8
11.2
12.6
14.0
15.2
16.6
18.0
19.4
COVER.
COVER.
COVER.
50 Hz, SW02-1 ON. Time for PUMP
ON in seconds
8.4
10.0
11.6
13.4
15.0
16.6
18.4
20.0
21.6
23.4
10SEP02 – 9B8949

Advertisement

Table of Contents
loading

This manual is also suitable for:

X-omat 1000aX-omat 1000j

Table of Contents