Mixing the Developer
and Fixer Solutions
Draining the
Processor Tanks
2B6841
Replenishment Solutions
[1]
Move the main Circuit Breaker CB1 to the ''O'' position.
[2]
Close the Developer and Fixer Drains. See Figure 12 on page 40.
[3]
Determine which type of chemicals is needed for the film processing cycle that
you selected. See the table on page 10.
• When mixing chemicals, follow all instructions and precautions.
• Do not mix more than a 2-week supply of developer and fixer replenisher.
[4]
Following all directions provided with the solutions, mix at least 19 litres
(5 gallons) of each solution.
• Drains must be made of chemically resistant, non-corrosive material.
Use PVC or the equivalent.
• The drain must have a minimum diameter of 7.6 cm (3 in.) and be free of
obstruction.
• Drain service must comply with all local codes.
• Do not make a solid connection between the hoses and the drain.
• Locate the drain within 1.5 metres (60 in.) of the Processor.
• The drain line should slope gradually downward to the floor drain.
[1]
Open the Fixer and Developer Drains. See Figure 12 on page 40.
The Wash Tank does not need to be drained.
IMPORTANT
NOTE
39