Recommissioning The Inverter - SMA SUNNY ISLAND 4.4M Operating Manual

Hide thumbs Also See for SUNNY ISLAND 4.4M:
Table of Contents

Advertisement

SMA Solar Technology AG
7. On the Sunny Island, fasten the enclosure lid following the
sequence 1 to 6 using an Allen key (AF 5) (torque: 6 Nm). The
teeth of the serrated conical spring washer must press into the
enclosure lid. This ensures that the enclosure lid is grounded.
8. Recommission the inverter (see Section 13.11, page 139).

13.11 Recommissioning the Inverter

If you have disconnected the inverter from all voltage sources and want to recommission it, proceed as follows.
Requirements:
• All circuit breakers in the AC distribution board must be open.
• All Sunny Island inverters must be connected correctly (see Section 6.7, page 63).
• All inverters must be closed (see Section 6.8, page 66).
• All Sunny Island inverters must be switched off.
• The fuse switch-disconnector of the battery fuse must be closed (see Section 6.9, page 67).
Procedure:
1. For systems with 1 Sunny Island, press the "On" button.
2. For systems with 3 Sunny Island inverters, press and hold the "On" button on the master until an acoustic signal
sounds.
3. For multicluster systems, press and hold the "On" button on each master until an acoustic signal sounds.
4. Establish a connection to the user interface of the inverter (see Section 8.1, page 104).
Operating manual
13 Cleaning and Maintenance
5
4
1
2
3
6
SI44M-80H-13-BE-en-15
6x
6x 6x
139

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents