5.2.2

Mounting in clinker facades

For mounting the installation boxes in clinker facades, perform the following points:
Fig. 12:
Mounting installation boxes in clinker facades
1. Chisel a hole according to the size of the outdoor station used into the facade provided.
The suitable template is enclosed with the flush-mounted installation box.
Dimensional drawings, see chapter 5.9.4 "Installation boxes - flush-mounted installation"
on page 59.
The installation depth of the flush-mounted installation box is 46 mm.
2. Insert the flush-mounted installation box.
Attention:
Ensure that the encircling "Collar" of the flush-mounted installation box rests on the
facade. The encircling "Collar" of the flush-mounted installation box must not be
submerged in the facade. The device can then not be mounted later.
Fix the flush-mounted installation box into the cut-out of the facade with the aid of the
elongated holes.
The hollow spaces between the flush-mounted installation box and the clinkers can be
filled with PU foam.
For this, break out the holes in the corners of the box angled at 45°.
Insert the extension tube of the PU foam and fill the cavities.
Use a low-expansion foam to prevent foam from penetrating the flush-mounted box.
If necessary, use foam cleanser to remove the contaminations.
No additional accessories are necessary for mounting.
3. Mounting the outdoor station.
see chapter 5.3 "Outdoor stations" on page 39.
System Manual
Connection, installation / mounting
│36