UPS5000-E-(60 kVA-125 kVA)
User Manual (Integrated UPS 3.0)
Figure 3-10 Adjusting the leveling feet
----End
Installing the Cabinet on an ESD Floor
A support is required when the UPS is installed on an ESD floor. The support
height depends on the height between the ground and the ESD floor.
Step 1 Lift the UPS onto the support and align the UPS mounting holes with those on the
floor.
Step 2 Level the UPS by adjusting the anchor bolts and using a level.
● Wrench an anchor bolt clockwise to elevate the cabinet, or wrench it
● To prevent cabinet tilting, adjust the four anchor bolts instead of one anchor
● Use a measuring tape for measurement when leveling the cabinet to ensure
● Do not remove anchor bolts. Otherwise, you need to rework them for use.
Step 3 Insert four M12 bolt assemblies into the mounting holes on the UPS and support,
and tighten the bolts.
Issue 03 (2022-01-19)
NO TICE
counterclockwise to lower the cabinet. The anchor bolts can be wrenched
within a range of 0–8 mm.
bolt.
that the height between the cabinet top and the floor is 2000 mm (tolerance
+3 mm).
Copyright © Huawei Technologies Co., Ltd.
3 Installation
67