11.12

Initial start-up

This section is directed towards the electrical specialist.
11.12.1

Check activation of the battery modules

If you do not carry out the initial start-up immediately following the installation of the battery modules, the
battery modules must be reactivated as described in chapter 11.11.9 beginning on page 59, chapter 11.11.10
beginning on page 60 and chapter 11.11.11 beginning on page 62.
The following steps are required for switching on the VARTA element backup energy storage system:
The network cable is inserted.
The fuse on the house network is switched on.
Switch the store "ON" with the on/off switch.
(The button is locked in the lower position.)
i
After switching on, it is necessary to carry out the
Until the conclusion of the Quick Install, the LED ring changes between the colours:
Green - orange - red.
The initialisation can be tracked on the LED ring on the on/off switch.