11 Assembly And Installation; Test Components - Varta element backup 6 Operating Manual

Hide thumbs Also See for element backup 6:
Table of Contents

Advertisement

ATTENTION
Material damage due to superimposition.
Deep discharge of the battery module.
The battery module
Have it commissioned within 20 weeks of delivery by the manufacturer or by an electrical
specialist.

11 Assembly and installation

This section is directed towards the electrical specialist.
11.1

Test components

Entry of water into electrical installations!
Short circuit and corrosion due to condensation water.
Installation of damaged components!
Possible danger to life.
38
Adhere to the storage conditions.
WARNING
Begin with the assembly only when the components have taken on room
temperature.
WARNING
Check all components for visible damage.
Do not install damaged components.
Contact VARTA.