Commissioning

6.
Commissioning
6.1

Final Inspection

46/66
POLARIS PROFESSIONAL
POLARIS Panel PC Professional 15" up to 24"
For electrical systems the relevant installation and operating specifications (e.g. Directives
99/92/EC and 94/9/EC, BetrSichV and the applicable national ordinances, EN 60079-14,
IEC 60079-14 and the DIN VDE 0100 series) must be observed.
The operator of an electrical system in a hazardous environment must keep the operating
equipment in an orderly condition, operate it correctly, monitor it and do the required
maintenance and repairs.
Before commissioning the devices, check that all components and documents are there.
Check the following requirements before commissioning the device:
Only open the terminal compartment with terminals for the supply and data line(s) once it
has been ensured that no potentially explosive atmosphere is present and that the power
supply has been turned off.
Has the reinforcement frame between the bracket and enclosure been inserted?
Is there no damage to seals, cable connections or glass panel?
Are the supply and data line(s) correctly wired?
Have the supply and data line(s) been tightened in the screw terminals?
Are all terminal compartments closed?
Have all cable glands been tightened and all open cable entries closed with blanking
plugs?
Only start the POLARIS (if a potentially explosive atmosphere is present) once the final
inspection has been carried out.
- for Zone 2 / 22
Technical data subject to change without notice..