Commissioning
Installation of »PLC Designer«
5
Commissioning
This chapter contains information on how to commission and integrate the controller into an
automation system.
Required accessories
Engineering PC with »PLC Designer« installed.
•
Standard network cable
•
5.1
Installation of »PLC Designer«
For the installation, download the »PLC Designer« from the download area on the Lenze
homepage to your PC and run the setup file.
www.Lenze.com à Downloads
5.2
Commissioning
Recommended sequence of the commissioning steps
1.
4Connect controller and Engineering PC
2.
4Set IP address on the PC
3.
4Start controller
^ 18
4.
4Create PLC program
^ 20
5.
4Create task
^ 21
6.
4Compile PLC program code
7.
4Establish connection between controller and »PLC Designer«
8.
4Log in to the controller (load configuration)
9.
4Parameterize controller
10.
4Device name
^ 26
11.
4Start PLC program
^ 25
16
^ 17
^ 17
^ 21
^ 22
^ 23
^ 21