Using Objet Studio
5–82
Scheduling Jobs
You can schedule jobs to be printed at a future time. For example, you can 
configure Objet Studio to start long printing jobs in the late evening and 
early morning hours.
To schedule a job:
1. Select a job in the Jobs Queue, and click 
2. In the Scheduler dialog box, set the Start Date and Start Time for the job. 
Click on the Start Date arrow to open a calendar.
Figure 5-120: Scheduler with calendar displayed
3. Click 
.
OK
Exporting Jobs (objzf)
You can save print jobs as compressed files.
For an explanation of objzf files, see "Exporting and Importing Objet Build
Trays" on page 58.
To export a print job:
1. Select a job.
2. On the pop‐up toolbar, click 
3. In the Save As dialog box, select a folder.
4. Click 
.
Save
Modifying the Job Manager Screen
You can change the size of the sections of the Job Manager screen, by 
dragging the panel edges. This applies to:
the Jobs Queue panel
the Time panel
the History panel
Similarly, you can change the way the screen area is divided between the 
main section (Jobs Queue/Time/History) and the panels on the right side of 
the screen.
You can collapse (hide) the right panels (Available Resources/Material 
Consumption/Tray View) by clicking the top of the panel.
Click again to display the panel.
 on the pop‐up toolbar.
.