7.7. Start-up of Digital Gateway and application
download
Power-On procedure
Before Power On, complete a visual check of power cable connection and overall
wiring of the switchboard. The Digital Gateway requires parameter settings to func-
tion correctly. Parameter settings are completed with MNavigate. If Digital Gateway is
configured with an optional single MView in a stand-alone configuration then the de-
fault settings can be applied. Otherwise the settings must be configured before
start-up.
Any change of configuration settings on the Digital Gateway requires restart of the
Digital Gateway. During Digital Gateway restart all communication on the switchgear
bus network as well as communication to DCS/PLS/PLC is stopped. After reboot is
completed all communications are re-established.
Power On the control voltage supply
The Digital Gateway boots automatically. At first the Digital Gateway performs internal soft-
ware checks and verifies that the data available on the CF card is correct.
At the end of boot sequence, the LED 7 & LED 1 (Run) should be on as a minimum.
Confirm operation
Once correct operation has been established it is then possible to proceed with system con-
figuration and application download.
1 TG C90 80 04
STAR T-U P OF DI G ITA L GAT EWAY A ND
43