6. Reinstall the transparent protective cover on the DC input connector of the power supply.
7. Connect the other end of the DC cable to a DC source following the correct polarity.
Do not move the unit with the power supply after the DC cables are installed.
Do not remove the DC power supply from the unit with the DC cable installed or the DC source turned on.
Grounding is required for DC power supplies and systems.
The DC power inlet in the power supply has two terminals labeled +DC and -DC and has a screw marked with
symbol to connect to earth ground. The DC power inlet has a clear plastic cover.
Unplugging the DC PSU from the system when the PSU is powered is not supported. The DC input power source
has to power off before removing the DC PSU from the system.

Verify the switch boots correctly

Before installing the switch in its network location, plug it into a power source and verify that it boots
correctly.
Procedure
1. Connect the power cord supplied with the switch to the power connector on the back of the switch.
Then plug the power cord into a properly grounded electrical outlet.
Aruba 6300F/M Switch Series Installation and Getting Started Guide | (xxxx Switch Series)