Mounting And Connecting The Synergy Manager And Synergy Units - SolarEdge SEK-I Series Installation Manual

Three phase inverter
Table of Contents

Advertisement

NOTE
Unused conduit openings should always be sealed.
Figure 14: AC and DC panels with drill guides at the bottom of the Synergy Manager
3. Locate the drill guides for conduits on the DC and AC panels. Drill entry hole(s) for
up to 2" conduit on the DC panel and 2.5" on the AC panel or drill entry hole for a
single conduit, within the boundary marked on the inner side of the DC panel (see
Figure 14 ).
NOTE
In some models, the DC panel has three drill entry hole(s) for up to 3"
conduits.
4. Position the DC and AC panels back at the bottom of the Synergy Manager and
torque the screws to 1.9 lb.*ft.
Mounting and Connecting the Synergy Manager and
Synergy Units
This section provides instructions for vertical installation of the inverter and horizontal
Inverter installed horizontally on a flat surface.
Three Phase Inverter with Synergy Technology P/N: SExxK-xxxxIxxxx SExxK-xxxxIxxxx
Chapter 3: Installing the Synergy Manager and Synergy Units
    36