first tighten the corner screws and then the two central screws.
 2. Access SetApp and select Commissioning > Status.
 3. In the Summary section, under Server Comm., make sure S_OK  is displayed
together with the selected communication option.
 4. Scroll down to the Communication section and check that the communication
options are as required.

Signaling Options

Alternative Power Source
Energy-generation systems (such as PV inverters) connected to the grid may consist of
different types of energy generating sources.
In some cases, when grid power is disconnected, PV inverters operate in parallel with
other voltage sources, such as generators.
When inverters operate concurrently with generators, they may be subjected to voltage
and frequency fluctuations that exceed trips, which are preset according to regional
grid connection requirements. To support simultaneous operation of the inverter and a
generator, the inverter extends its Voltage and frequency operating range once it
receives a Power Reduction Interface (PRI) signal indicating that grid power is
unavailable ("Alternative Power Source mode"). When the grid power is restored, the
inverter automatically reverts to its default country setting, which includes the original
Voltage and frequency operating range.
Figure 37 , shows an Example of Alternative Power Source System.
The Power reduction Interface (PRI) terminal block on the communication board (See
Figure 38 ) is used signaling the inverter to switch to Alternative Power Source mode.
Three Phase Inverter with Synergy Technology P/N: SExxK-xxxxIxxxx SExxK-xxxxIxxxx
Chapter 6: Setting Up Communication with the Monitoring Platform
Figure 37: Example of Alternative Power Source System
    73