  Pre-commissioning (Off-Grid)
Mobile device with SolarEdge SetApp application
Power bank: 60W output port, USB-C Power Delivery (PD): 20V 3A (not provided)
USB cable: 3.3 ft (1 meter), male to male, USB-C (not provided)
IMPORTANT NOTE
Commissioning should be performed in full daylight.
NOTE
When pre-commissioning multiple inverters, each inverter need to be
commission individually.
To pre-commission the inverter:
 1. Turn OFF and secure the AC circuit breaker in OFF position in the circuit breakers
panel.
 2. Verify that SolarEdge SetApp is installed on your mobile device.
 3. Remove the cover from the Power Bank input port at the bottom of the Synergy
Manager. Connect the USB cable between the Power Bank and the input port -
Upon connection, all LEDs light steady for one minute, and then alternate blue /
green.
NOTE
Alternating red / blue LEDs indicat a poblem with the power bank.
 4. Start SetApp on your mobile device and follow the on-screen instructions.
Three Phase Inverter with Synergy Technology P/N: SExxK-xxxxIxxxx SExxK-xxxxIxxxx
Figure 27: Pre-commissioning the inverter