Ups Installation - Delta DPH Series User Manual

Hide thumbs Also See for DPH Series:
Table of Contents

Advertisement

• Keep the installation area's temperature around 77 ° F (25 ° C) and humidity within 95%.
The highest operating altitude is 3280ft (1000 meters) above sea level.
• For safety concerns, we suggest that you:
1. Equip surroundings of the installation area with CO
2. Install the UPS in an environment where fireproof materials are used to construct the
walls, floors and ceilings.
3. Install the UPS on a floor that is made of noncombustible materials.
• Do not allow unauthorized personnel to enter the installation area and assign specified
personnel to keep the UPS keys.
5.3

UPS Installation

NOTE:
Please use appropriate equipment (e.g. forklift) to move the UPS.
Please follow the steps below:
Step 1
Before installing the UPS in a designated installation area, please double-check whether the
area's floor weight loading is sufficient to bear the UPS, external battery cabinet(s), external
maintenance bypass cabinet and handling equipment (e.g. forklift) to avoid accidents.
Step 2
For installation not against the wall, fix the six stands at the bottom of the UPS on the
ground to avoid UPS movement. Each stand requires a M12 expansion bolt (provided
by qualified service personnel).
(Figure 5-2: Cabinet Floor Fixing Points)
41
or dry powder fire extinguishers.
2

Advertisement

Table of Contents
loading

This manual is also suitable for:

Modulon dph series

Table of Contents