Commissioning; Inspection Before Commissioning; Commissioning Procedure - Sungrow SG30CX User Manual

Pv grid-connected inverter
Hide thumbs Also See for SG30CX:
Table of Contents

Advertisement

Commissioning

6

6.1 Inspection before Commissioning

Check the following items before starting the inverter:
All equipment has been reliably installed.
DC and AC switches are in the "OFF" position.
The ground cable is properly and reliably connected.
The AC cable is properly and reliably connected.
The DC cable is properly and reliably connected.
The communication cable is properly and reliably connected.
The vacant terminals are sealed.
No foreign items, such as tools, are left on the top of the machine or in the junction
box (if there is).
The AC circuit breaker is selected in accordance with the requirements of this man-
ual and local standards.
All warning signs & labels are intact and legible.

6.2 Commissioning Procedure

If all of the items mentioned above meet the requirements, proceed as follows to start
up the inverter for the first time.
step 1 Connect the AC switch or circuit breaker between the inverter and the grid.
step 2 Rotate the DC switch of the inverter to "ON" position.
step 3 Connect the DC switch (if applicable) between the inverter and the PV string.
step 4 Set initial protection parameters via the iSolarCloud App. For details, please refer to
Installing the
meet requirements, the inverter will normally operate.
step 5 Observe the LED indicator to ensure that the inverter operates normally. Refer to
LED Indicator"
- - - - E E n n d d
52
App", and
"7.4.2 Login
for details.
Procedure". If the irradiation and grid conditions
"7.2
"2.4

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sg33cxSg40cxSg50cx

Table of Contents