4 Mechanical Mounting
step 2 Lead the sling through the two lifting rings and fasten the tie-down strap.
step 3 Hoist the inverter, and stop to check for safety when the inverter is 100mm above the
ground. Continue hoisting the device to the destination after ensuring the safety.
step 4 Remove the lifting rings and reassemble the sealing screws released in Step 1.
Keep the inverter balanced throughout the hoisting process and avoid collisions
with walls or other objects.
Stop hoisting in the event of severe weather, such as heavy rain, thick fog, or
strong wind.