5. Using both hands to hold onto the workpiece, reference the scales on the Fixture at the left and right of
the exposed Tool to adjust orientation until the desired alignment is achieved. A slot is located on the
left-hand side of the Fixture and is used to designate the optimal location that the workpiece should
occupy for a cable tie cycle. Use the leading edge of this slot as shown below to align the workpiece
properly.
Work Bundle Aligned for Tie Installation:
6.
Once the workpiece is properly aligned relative to the measurement scale(s), move both hands
simultaneously in the direction of the tool jaws. Once the right hand actuates the paddle, a tie will be
dispensed by the PAT4.0. Once completed, the Tool jaws will retract, and the workpiece can be
removed.
OPERATION MANUAL
OPERATOR > READY
1 2 3 4 5 6 7 8 9 0
1M
TIE TYPE
MAINTENANCE
USE THE REFERENCE LABELS TO LOCATE
THE WORKPIECE RELATIVE TO THE TOOL JAWS.
THE GUIDE SLOT IS USED TO GAUGE THE DISTANCE
RELATIVE TO THE TOOL. THE CONDUCTOR(S) TO BE TIED
CAN BE LOCATED ANYWHERE BETWEEN THE TOP OF THE LABELS
AND THE BOTTOM OF THE SLOT.
WORK AREA
TIES USED
SAMPLE CONDUCTOR
BUNDLE