7
To upload a graphic, click Add New under Views and browse to your .view file.
8
Click Continue. When message appears File added successfully, click Close.
9
Click Close again.
10 Right-click on the programmable controller in the controller list and select Check Status from the list. The
status of the controller should say File Mismatch.
11 Click the Download All Content button.
12 Assign channel numbers to the physical points by selecting the controller in the navigation tree and going to
Properties page > I/O Points tab.
13 Configure the controller on the Properties page > Control Program tab.
14 Check out and commission the equipment.
To use an EquipmentBuilder control program
EquipmentBuilder allows you to choose your equipment file from a list of currently available equipment products
from the factory. If the factory equipment is not available in EquipmentBuilder, you must build a control program in
Snap. See Snap Help for detailed information on using Snap.
After creating a control program in EquipmentBuilder, download it to the Zone Ctrl II using the i-Vu® or Field
Assistant application.
NOTE The Airflow Control microblock is already set up and adjusted in all of the EquipmentBuilder programs for
this controller. You do not need to adjust the Airflow settings at all when using one of them.
Single duct control programs using the Zone Ctrl II
•
VAV Single Duct No Heat
•
VAV Single Duct Elec Heat
•
VAV Single Duct Mod Heat
•
VAV Parallel Fan No Heat
•
VAV Parallel Fan Elec Heat
•
VAV Parallel Fan Mod Heat
•
VAV Series Fan No Heat
•
VAV Series Fan Elec Heat
•
VAV Series Fan Mod Heat
•
VVT Single Duct No Heat
•
VVT Single Duct Elec Heat
•
VVT Single Duct Mod Heat
•
VVT Parallel Fan No Heat
•
VVT Parallel Fan Elec Heat
•
VVT Parallel Fan Mod Heat
Zone Ctrl II and
VAV Zone II Secondary Duct Installation and Start-up Guide
Error! No text of specified style in document.
Installing the Zone Ctrl II and VAV Zone II Secondary Duct into the i-Vu® application
29
CARRIER CORPORATION ©2019
All rights reserved