Sponge-Jet 70P Recycler User Manual page 21

Table of Contents

Advertisement

WARNING:
Lockout/Tagout unit before performing maintenance.
Checklist:
It is user's responsibility to set up a schedule for maintenance. Listed below is
a general check list.
1. Grease Bearings and motor. (Follow provided lubrication schedule.)
2. Inspect belt condition.
3. Check to see variable speed pulley is operating properly. (Open and close
both sides evenly during operation.)
4. Inspect RPM control lock is tight.
5. Inspect screens for holes in mesh.
6. When checking screens check clamp rings for proper seating.
7. If ball trays are installed check to see if balls are in place. (They may fall out
if screen has a puncture or a tear.)
8. Inspect rubber products, such as V-gaskets and discharge connectors.
9. Inspect nuts and bolts. (See torque specification.)
Nuts and Bolts
All nuts and bolts used to assemble unit are high grade and have been set to
proper torque at Sponge-Jet, Inc. Due to unit being under constant vibration
it is suggested that nuts and bolts be checked periodically during scheduled
maintenance.
BOLT SIZE
TORQUE (DRY)
lb-ft
1/4"-20 grade 5
8
5/16"-18 grade 5
17
3/8"-16 grade 5
30
1/2"-13 grade 9
106
TORQUE (LUBED)
N·m
lb-ft
11
6.3
24
13
41
23
144
94
SPONGE-JET 70P 70E USER MANUAL |
N·m
8.5
18
32
127
21

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the 70P Recycler and is the answer not in the manual?

Related Products for Sponge-Jet 70P Recycler

This manual is also suitable for:

70e recycler

Table of Contents