Final Installation Checklist; Self-Contained - Bennett Horizon 2 Series Installation Manual

Electronic with 708 electronics
Table of Contents

Advertisement

Item
1
Shear valve installed per valve manufacturer recommendations.
2
Self-contained pumps must have a vacuum actuated pressure regulating valve
when used with above ground tanks.
3
Self-contained pumps require a check valve.
4
All hanging hardware must be checked for continuity.
5
The units must be properly bolted to the island.
6
Vapor piping must not contain vapor traps.
7
Field conduits must be properly potted per local, state and national codes.
8
Equipment must be installed in conjunction with an emergency power cutoff to
remove all power from the equipment in the case of an emergency. Test this
system for proper operation.
9
All grounds must be properly connected per the installation manual requirements
as well as local, state and national codes.
10
Use of properly sized neutral breaking circuit breakers for the units involved.
11
All dispenser electrical power is wired to the same phase of electrical power.
12
Use twisted 3 wire cable or twist 3 wires together for the card reader
communications circuit.
13
New site wiring must be megger tested. Old site wiring must be additionally tested
for continuity and shorts using a digital meter.
14
Verify the correct brand panels, nozzles and hoses are installed for each grade.
15
Calibrate the meters per the procedure on page 30.
16
Close and lock all dispenser doors, covers and panels.

Final Installation Checklist

Procedure
26
Completed
105894 Rev G 12-6-16