3.3.1 Installing the UPSs
Context
When installing multiple cabinets, install connecting kits to combine and secure
the cabinets.
Procedure
Step 1 Install the UPSs in a parallel system using the single UPS installation method.
Step 2 Unscrew the connecting kit and put it through the reserved holes to connect the
two UPSs and then tighten the screws on the kit, as shown in
Figure 3-41 Connecting parallel plates
----End
Issue 02 (2020-11-10)
NO TICE
NO TE
You also need to connect parallel plates at the rear of the UPS.