Maintenance Schedule
TABLE 1.
Inspection
System Rinse
System Rinse (for
sprayers equipped
with Air Blow Out
systems)
: System Maintenance
M AINTENANCE SCHEDULE
A P P E N D I X C
AND REPLACEMENT PARTS
Frequency
1. Ensure the main product tank is cleaned and filled with at
least 100 gallons of fresh water or that the pump is
drawing fresh water from the vehicle rinse tank.
2. Park the sprayer in a safe location to unfold the booms
and spray.
3. Ensure the RCM - Sprayer product control mode is set to
Auto.
4. Enter a target pressure of 40-60 psi [275.8 - 413.7 kPa]
(for applicable NCV2 control modes) and an application
Daily after use
rate of 10-20 GPA [93.5 - 187.1 L/ha].
5. Set the test speed to 6 mph [9.7 km/h].
6. Enable the sprayer product pump.
7. Turn on all section switches and the master spray switch.
8. Continue to spray water out of the booms until all
chemical is flushed from the system or at least 30
seconds.
9. Turn off the Master Spray Switch.
1. Perform a system rinse.
2. Set the Hawkeye® 2 system to Manual mode.
Daily after use
3. Set the pump PWM to zero and NCV2 PWM to 50-75%.
4. Follow the vehicle manufacturer's normal procedure for
the Air Blow-Out function.
Procedure
85