This section provides recommendations and procedures for inspecting, installing,
and testing the power supply.

Basic Setup Procedure

See Table 2.1 for a summary of the basic setup procedure and an overall view of the
subsections in Section 2. Use the procedure as a quick reference if you are familiar
with the installation requirements for the power supply. If you want more
information, each step in the procedure refers to subsequent sections which contain
more details. Execute each step in the sequence given.
Table 2.1 Basic Setup Procedure
Step # Description
1
2
3
4
5
6
See Section 3. Local Operation for instructions about front panel operation, OVP,
OTP, shutdown, and using multiple supplies. You will find remote programming and
monitoring described in Section 4. Remote Operation.
Release 2.1
Action
Inspection
Perform an initial physical
inspection of the supply.
Installation
Install the supply (bench or rack
mount), ensuring adequate
ventilation.
Input Power
Connect AC input power.
Test
Perform functional tests for
voltage mode operation, current
mode operation, and front panel
controls.
Load
Connect the load.
Sensing
Connect sensing lines.
Reference
"Inspection, Cleaning, and
Packaging" on page 36
"Location, Mounting, and
Ventilation" on page 39
"AC Input Power" on
page 40
"Functional Tests" on
page 43
"Load Connection" on
page 45
"Local and Remote
Sensing" on page 53