5.3

TROUBLESHOOTING

5.3.1
CHECKING
CHECKING THE
CHARGE VOLTAGE
After having completely charged the battery, see 2.5 (BATTERY).
Connect a multimeter between the positive (+) and negative (-) battery
terminals.
After starting the engine, disconnect the fuse and connect an ammeter to
the ends of the wires.
Using a revolution counter, accelerate and measure the charge voltage and
current.
13.5 ~ 15.5 V / 1.0 A below 5000 rpm.
If the measured value is incorrect, check the rectifier, see 5.3.2 (RECTIFIER).
5.3.2

RECTIFIER

Disconnect the four-way connector (1) (coloured green).
Set a multimeter to the x 1 M
terminal from the rectifier side (inner male terminals).
-
White
White
Yellow
Red
Green
This test method provides an approximate measure of resistance. Where
possible, fit a substitute rectifier known to be in good working order to
test the charge system.
If the reading found deviates from the specified value, change the rectifier.
Release 00/2003 - 06
range and measure the resistance of each
Connect meter (+) to:
Yellow
Red
-
8-10 k
-
33-35 k
Green
33-35 k
-
-
ELECTRIC SYSTEM
-
+