7.5.1.6
Preparing cables for cable entries with cable glands
Prepare cables with an outer cable screen or shield for EMC bonding with the metal enclosure
of the cabinet as illustrated in Fig. 7-8.
2
Figure 7-8: Preparing power cables for cable glands
(1) Outer cable sheath
(2) Cable gland
(3) Conductor insulation removed to expose
cable shield
7.5.2

Connecting the cables

7.5.2.1
Checking the cable insulation
-
Check the insulation of each cable before connection and verify that the results are within
the specification of the cable manufacturer.
-
Leave the cable conductors unconnected at both ends until the commissioning engineer
has given permission.
3BHS213401 E01 REV H
1
3
4
5
6
(4) Plate
(5) Screen extension to be connected to
PE ground busbar
(6) Heat-shrinkable termination
ACS1000 AIR-COOLED USER MANUAL
07 ELECTRICAL INSTALLATION
93/184