7.5.1.5
Preparing cables for cable entries with sealing modules
As a standard, the cabinet is delivered for cable entry through the roof of the terminal
compartment. If cables are entered through the floor, swap entry plate and cover plate.
-
Prepare cables with an outer cable screen or shield for EMC bonding with the metal
enclosure of the cabinet as illustrated in Fig. 7-7.
1
2
3
4
5
6
Figure 7-7: Preparing power cables for sealing modules
(1) Sealing module
(2) Frame
(3) Conductive foil of sealing module
(4) Cable clamp
(5) Shrinkable sheath seal
(6) Heat-shrinkable termination
(7) Outer cable sheath
-
Install the sealing modules according to the instructions of the sealing module supplier.
3BHS213401 E01 REV H
7
8
9
10
11
(8) Cable sheath removed to expose cable shield
(9) Shield extension to be connected to PG busbar
(10)Screen extension to be connected to the
PG busbar
(11) Cable lug as specified by the cable supplier and
suitable for M12 bolt
ACS1000 AIR-COOLED USER MANUAL
07 ELECTRICAL INSTALLATION
92/184