1.6
• Mix the remaining 1/2 bag of concrete. Fill the Bottom Pole (ALE) with concrete until it reaches the top of the
rebar (about 15" from the top of the pole). Tamp the concrete down in the Bottom Pole with a broom handle
to remove air pockets. Clean all concrete off the outside of the pole. You may now remove the Alignment Frame
(BGW).
Stop assembly now. Do not continue the assembly until the concrete has been allowed to set for at least 72 hours (3 days). In humid
climates or wet weather, allow more time for the concrete to cure. Do not proceed until the curing process is complete.