6
|
Unit installation
6.3.2 Precautions when mounting the outdoor unit
6.3.3 To provide the installation structure
Installer reference guide
58
INFORMATION
Also read the precautions and requirements in the following chapters:
▪
"1 General safety
▪
"6.1 Preparing the installation
Check the strength and level of the installation ground so that the unit will not
cause any operating vibration or noise.
Use a vibration-proof rubber (field supply) in cases where vibrations may be
transmitted to the building.
Fix the unit securely by means of foundation bolts in accordance with the
foundation drawing.
Prepare 4 sets of M8 or M10 anchor bolts, nuts and washers (field supply).
(mm)
a
100 mm above expected level of snow
4
precautions" [
6]
4
site" [
48]
ERLA03DAV3 + EHFH03S18DJ3V
Daikin Altherma 3 R F