Completing Setup of the Unit From the NOC
1. Access the remote FrameSaver unit.
– For a unit installed using the procedure in Physically Installing the Unit and
Setting Up for Remote Access on page 9 , access the unit using the dedicated
management link, using the Node IP Address that was entered.
– For a Model 9128-II installed using the procedure in Installing and Setting Up a
Model 9128-II in Leased Line Mode on page 10, ping the FrameSaver unit
five times within five seconds on the troubleshooting access link. The unit
automatically configures the TS Access DLCI as a non-multiplexed
management DLCI and assumes the IP address on this management link is the
same as the destination address of the ping.
2. Configure specific frame relay options, like CIR (committed information rate), and
any other configuration options requiring input or changes from the default settings.
3. Configure each interface according to the local management interface (LMI ) and
assigned line conditions supplied by the service provider.
Configuration
Configuration
4. If SNMP traps are wanted, set up managers, select the desired traps, and
configure trap dial-out if desired (see Configuring SNMP Trap Managers and Trap
Dial-Out on page 16).
5. Set up the modem and, if trap dial-out is desired, the Call Directories (see Setting
Up the Modem on page 13).
6. If the unit is equipped with an ISDN DBM, set up the DBM (see Setting Up the
ISDN DBM on page 14).
7. Save the configurations.
8. Verify the entire path from the remote unit to the NOC NMS is functioning (see
Verifying the End-to-End Path on page 18).
9. Verify that data is being received (see Verifying That Data is Being Received on
page 23).
10. Verify that all PVCs, including Management PVCs, are configured; and see
whether the PVC is active or not (see Checking PVC Connections on page 24).
11. Verify the setup for backup, if applicable (see Verifying that Data Can Be Passed
Between DBMs on page 24).
The FrameSaver installation is complete.