Completing quick commissioning
• Press OK while the BOP-2 displays FINISH
• Select YES and press OK again
OK
The converter is now optimally parameterized for your particular application and motor specifications.
Motor data identification should now be run to complete commissioning. This can be done by switching
on the motor. Presently, the command source is set to digital input DI 0. Start the motor by energizing
DI 0.
Motor data identification
• Start the motor manually by using digital input DI 0
• The measuring process is set in motion. This can take several minutes – do not interrupt this process
• The motor is switched off when the process has been completed
• BOP-2 indicates that the measured values are now being converted into data
OK
After the motor data identifica-
tion has been performed, switch
the motor off and on again in
order to start normal operation
(using DI 0).