The lift has twelve lubrication points: two for each cylinder and four on the lift arm:
(See the oval images below with black frames). On these images shows the lubrication
points on the lift's right side and is represented with black numbers (1-6).
On the left side of the lift are the lubrication points mirrored, and is represented in text and
images below with red numbers (7-12).
Note! The images shows a ZAEHD lift, but the lubrication points are the same for a ZAHD.
1,
7
6,
12
(1.)
(2.)
Lowering the lift in the approximate
location shown on the image to the right.
Lubricate the points (1, 7), (6, 12) and
(3,
9)
again, and also (4, 10) and (5, 11)
ZAHD/ZAEHD-150/200/250
Tilt the platform a bit to avoid pressure against the body
work (1.) See position of the platform on the image to the
left. Lubricat the points (1, 7), (6, 12) and (3, 9). Tilt the
platform to position (2.) approximate 90° and lubricate the
points (2, 8)
2,
8
Lower the lift entirely as shown on the image to the
left. Lubricate the points (4, 10) and (5, 11) a last
time. The lubrication of the lift is now complete.
11
IE-0101
4,
10
5,
11