COMMISSIONING AND
START-UP WIZARD
Before commissioning, read
the warnings and instructions
listed in "Safety" on page 3!
Commissioning steps of SmartVFD
HVAC2
1
Read carefully the safety instructions in
"Safety" on page 3 and follow them.
2
After the installation, make sure that:
both the frequency converter and the motor
are grounded.
the mains and motor cables comply with the
requirements given in "Cable and fuse
specifications" on page 33.
the control cables are located as far as
possible from the power. cables (see "General
cabling rules" on page 37, step 2) and the
shields of the shielded cables are connected
to protective earth.
3
Check the quality and quantity of cooling air
("Cooling" on page 15).
4
Check that all Start / Stop switches
connected to the I / O terminals are in
position.
5
Connect the frequency converter to mains.