9.
FRONT SURROUND & CONTROL LINKAGE INSTALLATION
Fig. 20 Outer surround top location
Fig. 21 Control linkage
Fig. 22 Outer surround sides attachment
Fig. 23 Control linking bar & pivot
connection
9.1
Rotate the control unit clockwise until it contacts the end of the
spindle on the shut-off tap.
9.2
Pick up the outer surround and slide the control button upwards
as far as it will go. Make sure that the bottom of the linking bar is
higher than the bottom of the front surround. Locate the two lugs at
the top of the front surround in the slots in the convection box hood
(See figure 20). Swing the bottom of the surround sides back against
the convection box and lower the surround so that the lugs are fully
seated in the slots in the convection box hood.
9.3
Lift the bottom of the surround slightly clear of the
convection box to get access to the bottom of the control linkage.
Carefully slide the control button downwards while feeding the
bottom of the control linkage through the gap between the surround
fixing bracket and the burner supply pipe (see figure 21).
9.4
Place the surround fully back in position. Secure the
surround sides to the convection box brackets with the two screws
provided (See figure 22).
9.5
Align the hole near the bottom of the control linking bar
with that in the control pivot unit. Join them with the knurled
shouldered screw (See figure 23). Make sure that the isolating valve
is closed. Slide the control button fully from top to bottom and back
to make sure that the slide and pivot mechanisms move smoothly.
Note that some resistance should be felt when the slide button
reaches the "burner fully on" position.