the cooling system and installation environment
should be checked.
8. Open shut-off valve to the service line.
9. Reinspect the compressor for temperature and
leaks the following day.

6.4 SUBSEQUENT START-UP PROCEDURE

On subsequent start-ups, check that the proper
level is visible in the fluid sight glass and simply
COMPRESSOR OPERATION
press the START
When the compressor is running, observe the
instrument panel and maintenance indicators.

6.5 SHUTDOWN PROCEDURE

To shut the compressor down, simply press the
STOP
button.
Section 6
or AUTO MODE
button.