UPS5000-A-30 kVA & 40 kVA & 80 kVA
User Manual
Knock the expansion bolts into the holes until the expansion sleeve completely fits into the
hole. The expansion sleeve must be completely buried under the ground to facilitate
subsequent installation.
Figure 3-33 Installing an expansion bolt (unit: mm)
1.
2.
3.
4.
Step 3 Move the UPS to the installation position over its castors.
Step 4 Lower the four leveling feet at the bottom of the UPS using a wrench until all the four castors
at the bottom hang in the air and the leveling feet bear the whole cabinet weight.
Step 5 Secure the two L-shaped brackets to the front and rear of the chassis using eight M6 screws.
Issue 11 (2018-12-10)
Drill holes in the ground by using a hammer drill. The hole depth is 52 mm to 60 mm.
Partially tighten the expansion bolt and vertically insert it into the hole. Knock the
expansion bolt using a rubber mallet until the expansion sleeve is fully inserted into the
hole.
Partially tighten the expansion bolt.
Remove the bolt, spring washer, and flat washer.
Copyright © Huawei Technologies Co., Ltd.
3 Installation
62

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ups5000-a-40 kvaUps5000-a-80 kva

Table of Contents